Fort Bend County Waives $2 Billion in Equipment Taxes for Tesla Solar Plant
Commissioners approved a 35-year tax shield for a proposed $10 billion facility in Richmond, Texas, though Tesla has not yet confirmed the site selection.
By Alina Ndlovu ·

Fort Bend County commissioners voted 4-0 on Thursday to approve a package of agreements that provides up to 35 years of local tax relief for a proposed $10 billion solar factory.
The facility, named Project Crystal Sun, would be located southwest of Houston in Richmond. It is designed as a vertically integrated plant that manufactures solar products from silicon ingots to finished modules. Commercial production is targeted for the first quarter of 2029. Tesla has not yet confirmed it will build the plant in Texas.
The county package includes a Chapter 312 tax abatement, a Chapter 381 incentive agreement, and two foreign trade zone agreements with payment in lieu of taxes. For the first ten tax years, the abatement waives 100 percent of county property taxes on equipment and other tangible personal property. The start year defaults to 2029 but can be delayed to 2031 without further county approval. Tesla’s filing splits the $10.1 billion investment into $1.52 billion of real property and $8.6 billion of personal property. Land and buildings remain fully taxable at all times. Inventory is handled through Foreign-Trade Zone No. 149, with payments in lieu of taxes set at zero during the abatement period.
After the initial abatement period ends, the county returns 90 percent of the taxes Tesla pays on its equipment as an annual grant for 20 years. The county keeps the remaining 10 percent for its general fund. If Tesla averages at least 12,000 employees for two consecutive years within the first decade, the first five years of the rebate become a 100 percent grant. The rebate period also extends to 25 years, stretching the total deal to 35 years. This threshold is 2,288 jobs above the 9,712 positions Tesla says it will create.
Tesla must begin construction by June 30, 2027, to keep the benefits. It must start regular commercial production of solar cells by December 31, 2030. The company must invest $10 billion by the later of the end of 2031 or two years after production begins. Jobs are set to ramp from 2,500 to 5,000 to 7,500, reaching 9,712 by the fourth year at an average wage of $55 per hour. Tesla receives the full abatement if it reaches 90 percent of the job target, which is about 8,741 people.
Penalties for missing targets are limited. Missing a jobs or wage target for one year costs Tesla only that year’s break. Two straight misses allow the county to terminate the agreement. Full recapture of abated taxes applies only to material defaults such as missing the investment deadline or abandoning the plant for 12 months. A possible 15 percent penalty applies if unpaid taxes are not settled within 60 days. Grants already paid cannot be clawed back over a headcount shortfall. The county’s guaranteed minimum return is $2 million per year.
Tesla’s consultant Kroll estimated the project would pay $276.5 million in Fort Bend general taxes over 38 years without incentives. That figure peaks at $16.2 million in 2030. In its application, Tesla stated the Fort Bend site was not competitive with an unnamed site in another state. The competing state was redacted in the documents. The application cites Elon Musk saying at Davos in January that Tesla and SpaceX are working toward 100 gigawatts a year of US solar manufacturing. Fort Bend economic development director Carlos Guzman told ABC13 the county would have been eliminated from consideration without the agreements. The state must still approve the school-tax portion of the deal.